Dietrich Idaho Water Project 01-23-2014 install meter vaults.
01-23-2014 Dietrich Idaho Water Project. Replace meter vaults and water meters with Sensus iPerl meters, and Mueller coil type meter vault.
8:15-1:45: Getting ready to dig Brad Dotson service.
8:30: Digging Dotson service. 9:00 Dan McBride will take down fence over his service, informed us of culverts by service.
9:15: Digging Dotson service.
9:45: Plumbing Dotson service.
10:00: Laying electrical locate tape over conduit in trench at wellsite & backfilling.
10:15: Plumbing Dotson service.
10:30: Dotson plumbing done, meter in, water on, backfilling.
10:45: Smoothing backfilled trench at wellsite.
11:00: Digging Dan McBride service.
11:15: Hammering Auker service, digging around culvert at McBride.
11:30: Plumbing Auker, digging McBride.
11:45: Plumbing Auker, digging McBride.
12:00: Auker plumbing done, meter in, water on, backfilling.
12:15: Plumbing McBride.
12:30: Auker backfilled & done, digging Herb McCowan service, plumbing McBride.
12:45: digging McCowan, plumbing McBride.
1:00: McBride plumbing done, meter in, water on, backfilling, digging McCowan.
1:30: McBride done, plumbing McCowan.
1:45: McCowan plumbing done, meter in, water on, backfilling.