Dietrich Idaho Water Project 02-10-2014 Install Generator, Backfill Hole.
02-10-2014 Dietrich Idaho Water Project. Install generator, backfill hole, begin installing air valve.
1:15-4:30: Two electricians installing backup generator & control system. Jeremiah & Oscar backfilling hole in wellhouse with gravel. Started installing air-valve.