Dietrich Idaho Water Project 02-17-2014 install meter vaults.
02-17-2014 Dietrich Idaho Water Project. Replace meter vaults and water meters with Sensus iPerl meters, and Mueller coil type meter vault.
8:15-12:45: Getting ready to dig Cheri Miller service.
8:45: Digging Miller.
9:15: Digging Miller.
9:30: Digging Miller, electrical conduit next to service.
9:45: Miller old vault out.
10:00: Plumbing Miller service.
10:30: Miller plumbing done, meter in, water on, backfilling.
10:45: Backfilling Miller, digging William Bingham service.
11:00: Digging Bingham.
11:15: Broke Bingham pipe.
11:30: Plumbing Bingham.
12:30: Bingham plumbing done, meter in, water on, backfilling.
12:45: Backfilling Bingham.
2:00-4:30: Backfilling Bingham, digging Ballard.
2:15: Plumbing Ballard.
2:30: Ballard plumbing done, meter in, water on, backfilling.
2:45: Backfilling Ballard.
3:00: Ballard done, digging Andrew Shaw.
3:15: Digging Shaw.
3:30: Digging Shaw.
3:45: Plumbing Shaw.
4:00: Shaw plumbing done, meter in, water on, backfilling.
4:15: Backfilling Shaw.
4:30: Shaw done.